Clovis Pipeline Project
From July to October 2023, we installed eight miles of 8-inch steel pipeline along Curry County Road 10 and East Seventh Street in Clovis. The $8.9 million project replaced and modernized the existing 8-inch bare steel pipeline which was installed in the 1930s.
The new pipeline improves reliability and expands capacity because technological improvements allow it to be operated at a higher pressure than the earlier pipeline. We also brought the Clovis pipeline into compliance with current federal regulations, boosting safety and reliability for our customers.